What Information Does a Foundry Need to Quote a Casting?

RFQ ManagementBy Erik Anderson
Updated September 3, 2026

A foundry needs seven things to produce a firm quote: a 2D drawing with tolerances and a revision level, a 3D model in a neutral format, the alloy or an approved equivalent, both the estimated annual usage and the first-order quantity, the machining scope, any required inspection records, and the destination with an Incoterm. Anything missing is replaced by an assumption, and the assumption is priced conservatively.

The Minimum Quotable Package

ItemWhat it decides
2D drawing with revision levelWhich version governs, plus tolerances, datums and notes
3D model (STEP)Geometry, wall sections, feeding and gating study
Alloy or approved equivalentMelt availability, properties, heat treatment
Tolerance grade and critical featuresTooling class, process control, scrap rate
Annual usage and first-order quantityProcess selection and tooling amortization
Machining scopeWhether the shop machines, subcontracts, or ships as-cast
Records (FAI, PPAP, certificates)Inspection cost and calendar time
Destination and IncotermFreight, duty, and who carries them

Why Each Omission Costs You

Missing quantity is the most common gap. Tooling is amortized across the parts that follow it, so a shop that does not know your volume cannot answer the question you actually asked.

Missing machining scope is the most expensive gap. "Machined" means every feature to one shop and the listed features to another, and that single ambiguity produces the widest spread in a quote set.

Missing records are the slowest gap. First article inspection, PPAP level, material certificates and certificates of conformance all carry real cost. A foundry that discovers them after quoting will requote, and you lose two weeks finding that out.

A Test Before You Send

Ask whether a shop that has never spoken to you could produce a firm price from the package alone. If the answer is no, you are opening a conversation rather than issuing a request for quote. Both are legitimate, but they get different response rates, and suppliers triage incoming requests on exactly this kind of clarity.

How Buyer24 Helps

Buyer24 keeps every request structured the same way, so the same fields go out to every foundry and the responses come back into one comparison view regardless of format. Get started →

FAQ

Do I need to specify the casting process?

Not always. If you know the process, state it. If you do not, say the requirement is open and let the foundries propose, since sand, permanent mould and high-pressure die casting price very differently at different volumes and one of them may suggest a cheaper route.

Should I include a target price?

It is optional and it cuts both ways. A target price helps a shop tell you quickly whether the part is worth quoting, but it also anchors the response. Include it when you want a fast qualify or disqualify, omit it when you want a clean market read.

How many foundries should receive the package?

Three to five qualified shops is usually enough to price a specified part. A request that visibly went to fifteen foundries reads as a price-fishing exercise and lowers the quality of the responses you get back.

People also search for:

what to send a foundry for a quotecasting rfq requirementsfoundry quote packageinformation needed to quote a casting

Ready to Transform Your Procurement?

See how Buyer24 can automate your RFQ process, communicate with suppliers worldwide, and save you hours every week.